Monday, May 4, 2009

Update from Karla

According to Karla, the “Main” sewer line and “Main” water line installations in the Phase 1 construction area have been completed.

General Contractor, James Peterson Sons is currently working to install individual sewer and water laterals in the downtown area.

Commencing next Monday morning (May 04) the Highway Street (Hwy 33) Railroad crossing (between Ellison Street and Kansas Street will be completely closed. I have been informed that the RR track repairs/updates in this area will continue for a (3) week period of time.

In addition, Karla has informed me that some additional activity in the Phase 2 construction area will commence in the middle of next week…..week beginning May 04. Concrete/pavement removal will begin on the opposite side of the Rock River Bridge (near the old St. Malachy’s Church) and continue west to an area near or at the Barstow Street Kwik Trip Station.

Please be prepared for these travel/navigational changes.