Monday, September 28, 2009

almost done!

Stage 1:Most punchlist items are complete

Stage 2: paving the second half of STH 33 today. Trierweiler also is planning on pouring some intersections on Saturday, weather pending. Next week, working on curbs and gutters.

Stage 3: Larabee is almost covered with select crushed and base course. They are starting to trim that and are hoping to pave that tomorrow. Curb and gutter will be the next step on this stage.

Monday, September 21, 2009

latest info we have

Stage 1 – Most of the punch list items have been completed this week.

Stage 2 – The north half of the roadway was trimmed and paved. Next week, the south half of the roadway will be trimmed and paved. Topsoil was also placed from Grand to Chandler Street.

Stage 3 – Storm Sewer, Water Main, and Sanitary Sewer has all been completed. It is also being graded today. Next week, we will be placing pavement down on Larabee Street.