Monday, September 28, 2009

almost done!

Stage 1:Most punchlist items are complete

Stage 2: paving the second half of STH 33 today. Trierweiler also is planning on pouring some intersections on Saturday, weather pending. Next week, working on curbs and gutters.

Stage 3: Larabee is almost covered with select crushed and base course. They are starting to trim that and are hoping to pave that tomorrow. Curb and gutter will be the next step on this stage.