Activity continues in the Phase 1 and Phase 2 construction areas. DOT Project Engineer, Karla Knorr has reported that masonry contractor, Trierweiler Construction is continuing with sidewalk and colored concrete handicapped ramp installations in the Phase 1 construction area.
Another concrete activity that was initiated yesterday afternoon in the 300 block of
Some of the Phase 1 street signage may be erected next week coupled with some initial topsoil/landscape activity.
Most individual sewer and water lateral tie-ins in the Phase 2 construction area have been completed……..the only exception is an area under the Highway Street railroad tracks between Barstow Street and Main Street. That section will be completed sometime next week.
Two James Peterson Sons crews are also continuing to install storm drain/sewer in the Phase 2 area and a crew has begun to install breaker rock and base course stone between