Stage 1
Stage 1 opened to local traffic as planned--ON TIME!!! Yay for our state highway workers.
Stage 2
Grading and placing aggregate continues on Stage 2. Peterson is also preparing for sidewalk between Grand and
Stage 3
Stage 1
Stage 1 opened to local traffic as planned--ON TIME!!! Yay for our state highway workers.
Stage 2
Grading and placing aggregate continues on Stage 2. Peterson is also preparing for sidewalk between Grand and
Stage 3
Phase 1:
Construction activity occurring within the downtown intersection of
Efforts to erect the Lake & Vine intersection traffic signals are also occurring this afternoon.
In addition, landscaping activity and the installation of informational and directional signage will continue the remainder of this week and into next week. Pavement marking/paint striping is also occurring today.
Phase 2:
Both the eastbound and westbound traffic lanes between Columbia Street and Chandler Street now have paved concrete….concrete “tie-in” work continues at some intersections. Curb and gutter installations in the same area has started this week and will continue next week.
Storm drain/sewer installation activity will be completed later this week or early next week.
Grading and the placement of aggregate/stone in the
Stage 1
This week was definitely a busy week and next week should be more of the same! The
Next week, will should be finising the concrete in this intersection and the signals will hopefully be getting installed. Peterson will continue placing topsoil in Stage 1 and also prep for sidewalk at the Lake/Vine intersection as well as down
Stage 2
On stage 2, we poured half of the concrete pavement from