This week was definitely a busy week and next week should be more of the same! The Lake/Vine Street intersection was closed this past Monday and the crews have been working continually to get all the electrical work installed and concrete placed. Alliant Energy was onsite placing some of the decorative lights in the downtown area. Peterson also began placing topsoil on Stage 1.
Next week, will should be finising the concrete in this intersection and the signals will hopefully be getting installed. Peterson will continue placing topsoil in Stage 1 and also prep for sidewalk at the Lake/Vine intersection as well as down West Lake Street. Highway Landscaping will be onsite to finish placin signs and start laying sod. Pavement marking will probably begin at the end of next week as well.
On stage 2, we poured half of the concrete pavement from Grand Street to Chandler Street. The other half will be poured on Monday, August 3rd. Trierweiler will have a hand crew working on intersections in Stage 2 next week. Storm sewer is continuing in the Kansas Street Intersection. Hopefully storm sewer will be finished up by mid week. Grading will also begin next week from Valley Street to Larabee Street.
No comments:
Post a Comment