Thursday, June 18, 2009
Intersection closings
Monday, June 1, 2009
heads up on total road closures
Within the Phase 1 construction area all main line sewer, all main line water, all storm sewer/drains and all individual sewer and water lateral installations have been completed. The only exception is the immediate area encompassing the intersection of Lake & Vine Streets.
The Deere shutdown will help reduce traffic congestion and activity in this area and allow work crews to complete any necessary underground work activity within the intersection.
from Steve Tamminga
Monday, May 4, 2009
Update from Karla
According to Karla, the “Main” sewer line and “
General Contractor, James Peterson Sons is currently working to install individual sewer and water laterals in the downtown area.
In addition, Karla has informed me that some additional activity in the Phase 2 construction area will commence in the middle of next week…..week beginning May 04. Concrete/pavement removal will begin on the opposite side of the
Monday, April 20, 2009
Weekly update from Karla Knorr
Wednesday, April 15, 2009
new information on downtown routes
DOT Project Engineer, Karla Knorr is reporting this morning that the downtown intersection of